St. Benedict Catholic School
- Client / Owner
- Halton Catholic DSB
- Architect of record
- Snyder Architects Inc.
- Sector
- Institutional
- Delivery
- General contract, public tender
- Capital value
- On request
The challenge
Mid-winter start date with a September opening that could not move.
The Everstrong solution
Winter foundations under heat and hoarding, aggressive long-lead procurement, and close-out run from framing onward.
The result
Full school delivered on a seven-month schedule. Opened in September.